Each phase takes a certain perspective on a project. The objectives of the iterations inside the phases need to be
aligned with the goal of a phase. The following table provides general rules for the objectives of each phase, how many
resources are allocated and how long each phase should last compared with the overall schedule. At the end of each
phase, the success of each phase is evaluated and go-no-go decisions points for executive management offered.
|
Phase
|
Objectives
|
# / length of iteration (weeks)
|
Resources
|
Duration
|
|
Inception
|
Identify:
-
Coarse-grained requirements
-
Risks
-
Candidate architectures
|
~1-2 /
2-4 weeks
|
~5%
|
~10%
|
|
Elaboration
|
Prove:
-
Architecture
-
Critical functionality
-
High-level risk reduction
|
1-2 /
2-6
|
~20%
|
~30%
|
|
Construction
|
Build:
-
Continue detailing requirements
-
Functionality
|
1-n
2-4
|
~65%
|
~50%
|
|
Transition
|
Enable:
|
1-2 /
2-4
|
~10%
|
~10%
|
Example:
Schedule for a 4 month project, starting 9/1/2006 using the phase plan above.
|
Phase
|
# / length of iteration (weeks)
|
Duration
|
|
Inception
|
One 1-week Iteration
|
9/1/2006 –
9/8/2006
|
|
Elaboration
|
One 3-week Iteration
One 2-week Iteration
|
9/11/2006-10/13/2006
|
|
Construction
|
Four 2-week Iterations
|
10/16/2006-12/8/2006
|
|
Transition
|
One 2-week interation
|
12/11/2006-12/22/2006
|
|