Exporting To Microsoft Project

You can export a capability pattern or delivery process as an XML file which can be opened in Microsoft Project ®. This XML file will contain links to specific pages in the original method library.

Dependencies in the work breakdown structure are carried over to Microsoft Project. If there are circular dependencies in work breakdown structure, Microsoft Project will issue a warning but will accept the circular dependencies.

Roles are exported as Microsoft Project resources. They are connected to tasks or summary tasks as follows:

The following elements are not exported:

Microsoft Project sets the start and end dates for the project automatically. You will need to adjust them after the export has completed by using Microsoft Project.

  1. Use the File menu in the main toolbar and select export icon Export. The Export wizard will appear.
  2. Select MS project iconMicrosoft Project and click Next.
  3. Select a capability pattern or delivery process to export. Click Next to continue.
  4. Select the method configuration and export options that will be used to export the selected process.
    • Selected process
    • Method configuration
    • Publish the process web site
      • Publish the entire method configuration
      • Publish content that is only relevant to the selected process
    • Export only breakdown elements that are planned
    • Export effort estimates for the work breakdown elements
  5. Select the publishing options that will be used to publish the web site for the exported process.
    select publishing options
    Click Next to continue.
  6. Enter a Name: and Directory: for the exported file. Use the Browse button to navigate to the location for the exported folder.
  7. Click Finish to begin the export process