Milestone: Product Release Milestone
The end of the Transition phase is the fourth important project milestone, the Product Release Milestone, which is the result of the customer reviewing and accepting the project deliverables.
Main Description

The Product Release Milestone is the last major project milestone. During iteration assessment, you decide if the objectives were met, and then close the project. These are the evaluation criteria to keep in mind [KRO03]:

  • Users satisfaction and product acceptance
  • Stakeholder concurrence on acceptable resource expenditures compared to planned expenditures
  • Product is in production; therefore, a new development cycle for enhancements or maintenance may start
Properties
Predecessor
Multiple Occurrences
Event-Driven
Ongoing
Optional
Planned
Repeatable