|
Review iteration results
Towards the end of the iteration, the team should jointly assess whether the objectives and evaluation criteria
established in the Iteration Plan were met, and whether the team adhered to the plan and completed all
the work items committed to the iteration. It should use objective measures to the greatest extent
possible. To assess that a given work item is completed, the team should ensure that the corresponding test cases were
successfully run against it.
|
Demonstrate value and gather feedback
The team should demonstrate the product to customers, end-users, and other stakeholders to collect their feedback, or
better yet, have end users to use the product themselves. This should be done throughout the iteration, or at least in
a separate session towards the end of the iteration (see Guideline: Iteration Assessment). Work that is not completed should not be
demonstrated. Resulting knowledge, such as new functionality, requested changes and defects are recorded in the Work Items List, so project priorities, scope and duration can be refined in the
next iteration planning.
|
Perform a retrospective
Review with the team the approach taken to development and collaboration, the effectiveness of the development
environment, the suitability of the working environment, and other factors. Discuss what things went well, what could
have gone better, and how things could be changed to deliver better results. Capture assessment results in the current
Iteration Plan as well as stakeholder feedback and actions to be taken to
improve the development approach for next iteration. Record lessons learned in this iteration with a collection of
lessons learned for the entire project.
|
Perform a retrospective (end of phase)
When the assessment period coincides with the end of a phase the corresponding milestone review takes place. These are
informal reviews of the work accomplished where the team and stakeholders agree on moving the project on to the next
phase, spanning a set of iterations with a new common goal, in accordance with the emphasis of the following phase. For
more information, refer to Concept: Phase Milestones.
|
Close-out project
This step must be performed only when the iteration review coincides with the end of the project. Involve the team and
stakeholders in a final assessment for project acceptance which, if successful, marks the point when the customer
accepts ownership of the software product. Complete the close-out of the project by disposing of the remaining assets
and reassigning the remaining staff.
|
|