|
Establish a cohesive team
| Project planning, even at the summary level, should not be done in isolation since it outlines what the project will
deliver and how. The team starts by discussing who plays which roles and agrees on their responsibilities. The project
manager needs to make sure that staffing is made in accordance with the project's interests and that every necessary role
is covered. |
Determine project size and scope
The team produces rough size estimates for each item in the [Project Work] (see Guideline: Agile Estimation).
Discussions are held with the stakeholders to determine what is realistic to develop within the constraints of the
project. Stakeholder priorities and estimates from the team are used to guide these discussions.
If the project is feature-driven, the team looks at how many people they would need to complete these work items, which
gives them a high level understanding of project duration, staffing profile, and scope. If the project instead is
date-driven, the team assesses how much work can roughly be done in the time-frame given and using the available team.
Out-of-scope work can be considered in future releases.
|
Evaluate risks
The team identifies project risks, performs a qualitative risk analysis to assess their order of magnitude, and updates
the Risk List. The project manager facilitates the team decision about which risks they
should respond to, and which risks they should watch for.
Responses may include avoiding or mitigating risks, exploring opportunities or increasing the probability and positive
impacts of the risk. Depending on the case, work items may have to be added or removed from the [Project Work] to make sure that responses will be prioritized and handled by the team along with other project work. As it
is not feasible to plan responses for all risks identified, the team can decide to accept some of them. Risks to watch
will be communicated to stakeholders and remain on the Risk List. Actions will be determined only if they occur.
|
Outline milestones and iterations
[*** This is a new step. It is added because the 2nd paragraph of the prior 'Outline project lifecycle'
step needs to be contributed as a follow-on step from risk-value lifecycle. The 1st and 3rd paragraphs of
the original Outline project lifecycle step are appropraite here. NOTE: This content introduces a
dependency of this practice on Iterative Development. ***]
Define the iteration length and use it to assess target velocity (see Guideline: Agile Estimation). The number of items to be delivered in each iteration
will be set by the velocity of the team and the estimates for each item. The team uses the Work Items List to outline
what features to implement in what iteration, putting top priority work items first, including planned responses to the
higher risks or opportunities.
You don't need to spend too much time in doing this planning. The Project plan should document only a brief
summary of project milestones and 1-3 objectives for each iteration. Do not commit individual work items to
the plan, since this will force too much re-planning. The goal is just to create a high-level plan outlining
how the team can build the resulting application in the given set of iterations. Extra level of detail will
be achieved in other planning sessions throughout the project (see Task: Plan Iteration). You may need to revisit this plan later to adapt it based on what you will
learn by running the iterations (see Artifact: Iteration Plan from previous iterations).
|
Outline project lifecycle
Organize iterations into a set of phases. Each phase in the project lifecycle will end with a milestone aimed at
providing stakeholders with oversight and steering mechanisms to control project funding, scope, risk exposure,
value provided, and other aspects of the process (see Concept: Project Lifecycle)
|
Establish costs and articulate value
Develop a rough order of magnitude estimate for the costs of resources needed to complete project work items. A
simplified project costing model can be applied by multiplying the approximate cost per person for the
entire team by the length of an iteration to derive ongoing financial impact (i.e., cost per iteration). This first
round of planning should keep things very rough and flexible. The goal is just to articulate value against the budget
constraints of the project and help stakeholders to decide whether it's worth moving forward with the project or not.
If necessary propose options to decrease costs, such as removing from the scope low value and high cost work items.
|
Plan deployment
[*** Reword this to indicate that Project Work may be impacted, but don't show that being done here...it is the
task of iterative development (plan and manage iteration) to do that. ***]
Plan the strategy for deploying the software (and its updates) into the production environment. Discuss release
timeframe with the operations and support departments to ensure that your project fits into your overall corporate
deployment system. If you are replacing an existing system, decide whether you will run the new system in parallel with
it or you will perform a cutover. You may also have to negotiate with the owners of the systems that the new system has
dependencies on. Update the [Project Work] with additional work that may be needed for deployment. Add significant deployment risks to the Risk
List and, if necessary, make adjustments to the Project Plan.
|
|