Work Product Descriptor: Risk List
This artifact is a sorted list of known and open risks to the project, sorted in order of importance and associated with specific mitigation or contingency actions.
Based on Method Work Product: Risk List
Purpose
To capture the perceived risks to the success of the project.
Relationships
RolesResponsible: Modified By:
    Input ToMandatory: Optional:
    • None
    External:
    • None
    Output From
    Main Description
    This list identifies, in decreasing order of priority, the events that could lead to a significant negative outcome. It serves as a focal point for project activities and is the basis around which iterations are organized.
    Properties
    Optional
    Planned
    Illustrations
    Templates
    Key Considerations

    This list should capture the critical and serious risks. If you find this list extending beyond 20, carefully consider whether they are really serious risks. Tracking more than 20 risks is an onerous task.

    Tailoring
    Representation Options

    Optional: list of risks captured in the project plan

    In this approach you put the overall risk list in the project plan. The iteration plan will contain only the tasks you will be doing during the iteration to mitigate the risks. This will ensure that the iteration plan contains only iteration information. The project plan has to be revisited constantly as you updated risks.

    Option: list of risks captured in the iteration plan

    In this approach you enter the overall risk list in the current iteration plan. This approach ensures that you look at the risk list at each iteration, as it is part of your iteration plan. The only drawback is that your iteration plan will contain information that is not relevant to the current iteration. All the risks you have not mitigated during the iteration have to be transferred to the next iteration plan.