The Initial Operational Capability Milestone is the third major
project milestone. During iteration assessments in Construction, keep
these evaluation criteria in mind [KRO03]:
- Product release is stable and mature enough to be deployed in the user
community.
-
- The beta product is ready to be handed over to the users.
- All functionality has been developed and all alpha testing (if any)
has been completed.
- In addition to the software, a user manual has been developed, and
there is a description of the current release.
-
- Actual resource expenditures compared to planned expenditures are acceptable.
Note:
In case the project fails to reach this milestone, an iteration can be added
to Construction, thus postponing Transition. |