The Lifecycle Objectives Milestone is the first major project milestone. During
the iteration assessment, the following evaluation criteria
should be met [KRO03]:
-
Stakeholder concurrence on
-
- scope definition
- initial cost and schedule estimates
- definitions and priorities for initial set of requirements
-
risks identified and mitigation strategies proposed.
Note:
The project may be aborted or reconsidered if it fails to reach this milestone.
|