Task Descriptor: Conduct Scrum daily meeting
Daily team gathering for regulating development and test activities.
Based on Method Task: Conduct Scrum daily meeting
Relationships
RolesMain: Additional: Assisting:
InputsMandatory: Optional:
  • None
External:
  • None
Outputs
Steps
Preparing
Everyone updates the planning ( this sprint's backlog) by updating the remaining work on each respective tasks, which leads to a Sprint Burndown Chart.
Gathering all together

Each team member express himself one after one, answering to 3 questions on:

  1. what has been done since the previous daily scrum
  2. What will be done today
  3. Experienced problems

This meeting should occur with all team member standing up in a circle, with Sprint Backlog and up-to-date Sprint Burndown Chart before their eyes.

Consolider
The up-to-date Sprint Backlog helps to make a decision on adjusting the Sprint Goal. It must be kept in mind that a sprint is time-limited (timebox) and that it is preferable to remove initialy forecasted content rather than getting late.
Submitted problems are solved during Manage problems initiated by the Scrum Master.
Properties
Predecessor
Multiple Occurrences
Event-Driven
Ongoing
Optional
Planned
Repeatable