Prepare the demo
The meeting preparation must not exceed one hour.
|
Perform the demo
The team presents the partial product, result of its development tasks, through a demo of the implemented requirements
(user stories). Only fully completed (and tested) requirement implementations (et testées) are presented. This allows to
get an objective measurement of the work progress.
|
Evaluate Sprint results
The Product Owner and attending stakeholders (customers, users) ask questions to the
team, give impressions, make proposals and change requests. The Product Backlog is enhanced with found bugs and enhancement requests.
|
Calculate actual velocity
The Sprint Velocity is the sum of all associated points to requirements checked as fully
implemented. It is then compared to the one from previous sprints, usually through a Release Burndown Chart.
|
Adjust the Release planning
Conditions may have changed since the last release planning:
-
items may have been added, or deleted, estimations updated,
-
item prioritization has been changed,
in addition, average velocity may have evolved.
The Release planning is adjusted, taking into account these new parameters.
|
|