During a sprint, no one can modify the selection of backlog items, done at the beginning of the sprint: the sprint
scope remains unchanged.
However, anyone, even a external stakeholder, can suggest new items for later. These items are studied and prioritized
by the product owner prior to next sprint planning.
Bugs and enhancement requests coming from partial product tests done at the end of previous sprint are also used to
update the backlog.
|